City of Farmersville, CA

Cameron Creek Colony Emergency Water Supply Project

The Cameron Creek Water project involved multiple agencies, groups, and individuals to get the project constructed without undue delay. It was a true team effort of the City of Farmersville, Tulare County Board of Supervisors, Tulare County Resource Management Agency, Tulare County Local Agency Formation Commission, Self Help Enterprises, Quad Knopf, Inc. (QK), and West Valley Construction. California State University Fresno and BSK provided additional support during the outreach and preliminary engineering, respectively.

QK provided the engineering design of 7,262 lineal feet of 8-inch water main, installation of 6 fire hydrants, 10 control valves, and 106 new water services to provide domestic water service to Cameron Creek Colony without an impact on Farmersville’s budget or without incurring a debt service that the severely disadvantaged community could not afford. Construction Management was also provided for the project.